24/02242/S36 unknown refuse Last updated 03/04/2026, 00:57

Consultation for the construction and operation of 6 wind turbines at Cruach Clenamacrie Wind Farm, each with a height of 200 metres, including associated infrastructure like a Battery Energy Storage System and compound.

Electricity Generation consultation

Glenlonan, Oban, PA34 4QE

PA34 4QE

Full Proposal

Section 36 consultation: Cruach Clenamacrie Wind Farm (ECU ref: ECU00004841) to construct and operate 6 wind turbines with ground to blade tip height of 200 metres, and associated infrastructure including Battery Energy Storage System and compound (BESS)

Application Timeline

Application Registered
06/12/2024
Application Validated
06/12/2024
Target Decision Date
02/01/2025
Committee Date
N/A
Decision Made
21/01/2026
Decision Issued
22/01/2026

Case Officer

Applicant

Scottish Government