25/01342/S36 unknown refuse Last updated 03/04/2026, 02:29

Consultation for the Giant's Burn Wind Farm to erect 7 wind turbines with varying heights and a battery energy storage system, seeking a 50-year operational period.

Electricity Generation consultation

Dunoon, PA23 7UN

PA23 7UN

Full Proposal

Section 36 Consultation: Giant's Burn Wind Farm (ECU ref. ECU00005007) for the erection of 7 variable pitch (3 bladed) wind turbines (5 each with a maximum blade tip height of up to 200m and 2 up to 180m) along with a battery energy storage system (BESS). The application seeks an operational period of 50 years.

Application Timeline

Application Registered
25/07/2025
Application Validated
25/07/2025
Target Decision Date
21/08/2025
Committee Date
18/02/2026
Decision Made
19/02/2026
Decision Issued
20/02/2026

Case Officer

Applicant

The Scottish Government

More Information